Penn Yan Central School District
				
				
					Penn Yan, NY
				
                
    Penn Yan Central School District
2021 Capital Improvement Project
- Site design at three schools.
 - Exterior stairs and drainage improvements.
 - New walkways and fencing, sidewalk replacement.
 - Pavement reconstruction at parking lots and bus loop, reconstruction of drop-off area.
 - Paved play area.
 - Site work related to site lighting.
 - Bleacher replacement with new concrete pad.
 - Site work associated with building additions.
 - Retaining wall replacement.
 
2017 Capital Improvement Project
- Site work associated with a secured building entrance.
 - Parking lot and circulation improvements.
 - Replacement of synthetic turf field at Penn Yan Academy stadium.
 - Structural spray resurfacing of the athletic track and field events.
 - Installation of permanent lacrosse netting.
 - Fencing and gate replacement.
 - Site work associated with a new Transportation Center.
 
2012 Penn Yan Academy
- Site work related to three building additions.
 - Scope of services included improvements to existing bus loop and front walkway, drop-off areas, sidewalks, installation of stairs, ramps, access road, parking lot, loading dock, and retaining wall, as well as development of a courtyard area.
 - Site preparation, grading, storm water management and drainage, circulation improvements, lawns and plantings.
 - Preparation of site sanitary plans and sanitary analysis.
 - Five new tennis courts, converting existing tennis courts into parking, and paving of the existing student parking lot.
 - Site plan preparation and site work associated with playscape replacement at the elementary school and installation of visitor bleachers at the athletic facility.
 
2004 Capital Improvement Project
Elementary/High School Additions
- Responsible for evaluating numerous site configurations related to various additions to achieve the best solution for the school district.
 - Scope of site work included: a 400 meter all-weather track, multiple grass playfields, synthetic turf playing field, circulation and parking improvements.
 - Storm water management and realignment of a channelized stream.
 - Subsurface irrigation system for the synthetic turf surface.
 