West Seneca Central School District
				
				
					West Seneca, NY
				
                
    West Seneca Central School District
Multi-Phase 2018 Capital Improvement Project
Phase 1
- Removal of existing 6x6 lane track and replacement with new 8x8 lane broken back track at both schools.
 - New synthetic turf field within the track at both schools.
 - Related athletic stadium improvements at both schools including 1,500-seat bleachers with press box, LED field lighting, scoreboard, field events including steeplechase.
 - Storm water management improvements including SPDES Permit.
 
Phase 2
- Visitor parking to bus loop.
 - Replacement of existing roadway and new sidewalk including storm water management to mitigate existing drainage issues.
 - Storm water management improvements including SPDES Permit.
 - Vehicular and pedestrian circulation, parking, and pavement improvements.
 
Phase 3
- Tennis court replacement.
 - Storm water management including SPDES Permit.
 - Concessions plaza.
 
Phase 4
- Sidewalk and curb replacement.
 - NYSDOT coordination for concrete apron replacement.
 - Parking lot improvements.
 - Storm water management.
 - Bus parking and circulation improvements.
 - Conversion of existing tennis courts into hardscape play area.
 - New one-way road for parent/student drop-off.
 
